Following on the success of FM Logistic Distribution Center project in Bac Ninh, TUAN LE proudly continues working with FM Logistic for their second project in Binh Duong Province as the main contractor with a contract value of 6 million USD.
The new distribution center covers an area of 20,000m2 featuring high level of automation through automatic classification machine, packaging machines and robots.
After 11 months of construction, the new warehouse was successfully delivered to our client, meeting all requirements in terms of safety, quality and schedule.
- PROJECT NAME
- FM LOGISTIC BINH DUONG
- LOCATION
- VSIP 11 IP, BINH DUONG PROVINCE, VIETNAM
- CLIENT
- FM LOGISTICS
- VALUE
- USD 6 M
- CONTRACT DURATION
- 11 MONTHS
- CONSULTANT(S)
- ARTELIA GROUP, ROYAL HASKONING
- SCOPE OF WORKS
- MAIN CONTRACTOR